On 26 November 2026, inspectors at the Farciennes/Aiseau-Presles site found work still underway on a nearly finished building of about 30,000 m², although the amended planning permit had been revoked on 16 August 2026. Roughly 300 workers were reportedly on site without valid permits, and Walloon authorities ordered construction to stop.
Greenpeace Belgium filed an urgent request on 23 November 2026, using satellite imagery and drone footage. The roughly 53-hectare site was originally permitted for three air-cooled data centers with a combined capacity of 160 MW; the amended permit approved in April 2026 was revoked after citizen appeals over drought and water use in the region.