Bogotá Metro will begin commercial operation in March 2028 without waiting for all related urban works to finish. According to Empresa Metro de Bogotá manager Leonidas Narváez, 60% of the public space tied to the infrastructure will be ready by then, with the remaining 40% completed in the following months. Platforms, bike lanes, plazas, green areas and street furniture are among the works still pending. The relocation of utility networks grew from 129 to 320 km, adding COP 123,000 million in costs for this component.
Narváez said stations will have the necessary access and safety conditions for passenger entry and exit from the start of operations.